Colombo Port’s Eastern Terminal is expected to reach 50% capacity by the end of November as it brings more container-yard lanes into operation, Deputy Ports and Civil Aviation Minister Janitha Ruwan Kodithuwakku said.
Speaking during an inspection on 27 November, the deputy minister said one yard lane was operating and work was underway to bring ten others into use. The yard uses rail-mounted gantry cranes to move containers.
Daily Mirror reported that the terminal was handling 20 to 30 containers an hour in its initial operations, according to the deputy minister. The 50% figure is a target for the rollout.
How the container yard is being brought into use
Rail-mounted gantry cranes move containers within the yard and support the work of loading, unloading and stacking them. Bringing lanes into use in stages gives the port a way to assess how the equipment and yard operations perform as more of the terminal comes online.
What counts as progress
The deputy minister cited an initial handling rate of 20 to 30 containers per hour. That figure and the 50% capacity target measure different things. The hourly figure describes initial operations, while the capacity target concerns how much of the terminal can operate. Further updates from the port will show whether the remaining lanes started operating on schedule.